Abstract

A calculation method of the number of shunting single trips for meeting the task volumes of shunting operations at a passenger station is developed. The computation of the single trips numbers is based on the train schedule and technological processes of the station and the car depot. The types of shunting single trips are analyzed, the required numbers of shunting single trips are calculated for specific shunting areas. The results of empirical trip are represented, which are in line with the results of computation.

Author Biographies

B. Ye. Bondar, Dnipropetrovsk national University of railway transport named after academician V.Lazaryan

B. Ye. Bondar

Ya. V. Bolzhelarskyi, Dnipropetrovsk national University of railway transport named after academician V.Lazaryan

Ya. V. Bolzhelarskyi

Published

2006-06-25

How to Cite

Bondar, B. Y., & Bolzhelarskyi, Y. V. (2006). DETERMINE THE REQUIRED QUANTITY OF SEMI TIME-TABLED TRAIN TO EXECUTE A GIVEN WORKLOAD MANEUVERING LOCOMOTIVES FOR PASSENGER STATION. Science and Transport Progress, (11), 112–115. https://doi.org/10.15802/stp2006/18683

Issue

Section

OPERATION AND REPAIR OF TRANSPORT MEANS